OnlineNW finally has their head-end cabinet in place! They ran into some issues with the original plan and had to move to another location. That required them to rebore the connections to it, which slowed the construction process down a bit. Now that the cabinet is in place, they are installing the equipment and connecting it up to their network.

Splicing is underway and they are continuing to build the mainline in the West Churchman area. 6th is done, as is 5th. They are currently working on Pacific Hills and that is going well. They are looking to hook up their first customers shortly. OnlineNW will let us know the connection dates as soon as these are scheduled!